Clive's
UndergrounD Line Guides"And we trundled and jogged - the train and I
Through cuttings that cut through - who knows?
Till we stopped at a single platform
And sat there in repose."- Shoreditch
Alan Gibley
East
London Line![]() History |
![]() Dates |
![]() Features |
![]() Services |
![]() Topology |
![]() Layout |
![]() Depots |
![]() Connections |
![]() Rolling stock |
The East London Line is the only LU line that was planned and built as a main-line railway, but its history goes much further back than that.
The first tunnel under the Thames was proposed in 1798, but nothing came of it. However, four years later the Thames Archway Company was formed to build a tunnel from Rotherhithe to Limehouse in the docklands area of London, and construction started in 1805. After initial problems, Richard Trevithick was appointed as engineer, and by the start of 1808 the initial drift - 1.5 m (5') high and 0.9 m (3') wide - reached from the southern shaft all the way to the low tide mark on the northern shore, only 60 m (200') or so short of its target. However, on 1808-01-26, a breach in the tunnel roof flooded the workings, and the project was abandoned.
Ten years later, in 1818, Marc Brunel - father of the more famous Isambard Kingdom Brunel - patented the first version of the tunneling shield. Five years later one of the Archway company's promoters learned of this, and backers were found for a new tunnel, about a kilometre west of the previous site, joining Rotherhithe to Wapping; construction started on 1825-03-02 with Marc in charge. The tunnel was intended to be used by road traffic, with 12m (40') wide spiral ramps coming down from the surface, but the first stage of the project was to dig the southern vertical access shaft and drive under the river, using a shield, to eventually meet the northern shaft (which was dug somewhat later).
Test bores in the riverbed seemed to show a good solid layer of clay a little below it, so Brunel decided to stay in the clay by placing the tunnel roof only 4.3 m (14') below the river bed. In fact, the clay was riddled with faults allowing water to leak into the tunnel, and several times breakthroughs of the Thames flooded the workings; the first such turned out to be at a point where dredging of the riverbed for gravel had brought it even closer to the tunnel.
Due to these and other problems, the project ran through a succession of engineers in charge, including Isambard Brunel at the age of 20. The company's capital was exhausted, and work had to stop completely several times - during one of these hiatuses, the tunnel gained the nickname of "the Great Bore". During the final stages of the work, a driftway was dug from the northern shaft to the almost-complete tunnel, and when they met, Isambard's 3-year-old son Isambard Kingdom Brunel III was handed through to become the first person ever to make the complete crossing under the Thames and, probably, through any tunnel under water. Meanwhile Marc Brunel was knighted in 1841 for his work on the tunnel.
The tunnel finally opened on 1843-03-25. Funding for the road access ramps was never found, so it was only accessible by walking down spiral stairways in the construction shafts. The final tunnel was 11.6m (38') wide and 6.9m (22'6") high, with a dividing wall - complete with ornamental arches - down the centre. Large enough for a good-sized road, and more than enough for a double-track railway, it was instead just carrying a trickle of pedestrians (who could easily hear ships' propellers in the river above, because of the closeness of the river bed); market stalls were also set up.
The tunnel survived as a curiosity for over 20 years. Finally, in 1865, various people involved with the tunnel formed the East London Railway, which purchased it to form part of an underground rail link between the GER at Liverpool Street (where through trains via the ELR would reverse) and the SER and LBSCR, at New Cross (1) and New Cross Gate respectively; a third connection ran to the LBSCR at Old Kent Road. The first part of the link, from the southern lines through the tunnel to Wapping, opened in December 1869 (the tunnel had remained in use as a footpath until July) while the remainder was opened 7 years later. Between Wapping and Shadwell the line ran through a second tunnel, this time along the bottom of a dock (which has since been filled in).
At Spitalfields a branch turned off into extensive sidings underneath the corresponding GER coal depot (and with a vertical hoist linking them); there were plans to tunnel to meet the GER line at Cambridge Heath, but these never came to fruition and the tunnel dead-ended only 350m from the junction.
For many years trains ran to a range of destinations south of the river, such as Croydon, Addiscombe Road, and even Brighton, as well as to a separate terminus at New Cross (2). The ELR never owned or operated its own trains, always relying on others. In 1884 the line was leased to a consortium of the five (six from 1885) companies using it, and on 1925-01-01 it was transferred to the Southern Railway (which had absorbed three of the six lessors), who immediately leased it back to the consortium.
As part of the completion of the Circle Line, a link was built from the Circle at Aldgate to the ELR, and both the Metropolitan and the Metropolitan District Railways ran trains on to the line from their respective Hammersmith termini, initially seeing it as a way to expand southeastwards (for the first 5 days trains ran in service as far east as Liverpool Street or Mansion House, then empty to St. Mary's, and then in service again on the ELR). The latter company abandoned the services in 1905 and the former in 1906, leaving the line to the main-line companies, who saw it mostly as a goods rather than passenger route. In 1913 the Metropolitan Railway came back to the line, providing passenger services throughout, something which has continued ever since (albeit under varying names). Initially trains ran from both southern termini to Shoreditch and to South Kensington via Edgware Road and High Street Kensington; the former service remains essentially unchanged, but the latter was diverted to Hammersmith on 1914-02-09, reduced to peak hours only on 1936-05-04, and ceased in 1941.
In 1939 there was concern that bomb damage could flood the under-river tunnel, after which the water would rise through the shaft at Rotherhithe station and flood the surrounding low-level ground. Therefore a double floodgate was installed at the north end of the station.
![]() Photo [382kb] and info |
The line eventually fell into LU ownership at nationalization. It remained a branch of the Metropolitan (becoming the "Metropolitan Line - East London Section" in March 1970) until the 1980s, when the separate identity was restored. The Underground companies, and later LU, never served Liverpool Street from the East London Line, as the through service had ended at electrification, but regular goods traffic came from there until 1962 and occasional passenger services were to run until 1966 when the link was severed. |
The line was closed in 1995 to carry out various repair work and to construct Canada Water station. The most significant part of the work was to seal the Thames Tunnel against leaks by "shotcreting" it. A legal conflict with architectural interests wishing to preserve the tunnel's appearance (and disputing the need for the treatment anyway) extended the closure, which was originally planned to last only 6 months or so. Following an agreement to leave a short section at one end of the tunnel untreated, and more sympathetic treatment of the rest of the tunnel, the work went ahead and the route reopened in 1998. This extended closing was partly due to deterioration of other parts of the infrastructure, which in turn was partly because of the lack of regular maintenance during the extended closing and the inability to predict when such maintenance could restart - a vicious circle! Reopening of Shoreditch station was delayed several months because, at the last minute, the Railway Inspectorate required "Moorgate control" to be installed there.
![]() Photo [402kb] and info |
The line is now being integrated into the London Overground network, after which it will no longer be an LU route. Shoreditch station finally closed in June 2006, with the rest of the line following in December 2007. At the north end, the line is being extended on a new alignment from north of Whitechapel (abandoning Shoreditch) to meet the former North London Railway (NLR) trackbed from Broad Street to Dalston Junction, from where it will continue to Highbury & Islington. At the other end, the line will extend in two directions, to West Croydon (with a branch to Crystal Palace) and to Clapham Junction, which involves reinstating a link from Silwood Junction to Old Kent Road Junction. |
| 1839-06-05 | ![]() |
New Cross Gate [London & Croydon Railway, later LBSCR] |
| 1847-09-30 | ![]() |
New Cross Gate |
| 1849-05-01 | ![]() |
New Cross Gate [LBSCR] |
| 1850-09-26 | [0] | [Dalston West Junction] to Highbury & Islington opened [NLR] |
| 1850-10- | ![]() |
New Cross (1) [SER] |
| 1858-09-01 | ![]() |
Canonbury |
| 1865-11-01 | [2] | Broad Street to [Dalston West Junction] opened [NLR] |
![]() |
Hoxton | |
| 1867-09-02 | ![]() |
Haggerston |
| 1866-08-13 | ![]() |
Old Kent Road [LBSCR] |
| 1869-12-07 | [2] | New Cross (2) to Wapping opened [LBSCR] |
![]() |
Canada Water | |
| 1870-12-01 | ![]() |
Canonbury |
| 1871-03-13 | 0 | Old Kent Road to Surrey Quays opened [LBSCR] |
| 1872-11-04 | ![]() |
Bishopsgate [GER] |
| 1874-02-02 | 0 | Bishopsgate to Liverpool Street opened [GER] |
| 1876-04-10 | 3 | Wapping to Bishopsgate opened [LBSCR] |
| Bishopsgate to Liverpool Street started [LBSCR] | ||
| 1876-07-01 | 0 | New Cross Gate to Surrey Quays opened [LBSCR] |
| 1876-10-31 | New Cross (2) to Surrey Quays closed | |
| 1880-04-01 | 0 | New Cross (1) to Surrey Quays opened [SER service to Liverpool Street] |
| 1880-10-01 | ![]() |
Mildmay Park |
| 1884-03-02 | Shadwell (1) to Liverpool Street withdrawn [SER] | |
| 1884-03-03 | 0 | Shadwell (1) to St. Mary's opened [SER] |
| 1884-09-30 | New Cross (1) to St. Mary's withdrawn [SER] | |
| 1884-10-01 | ELR leased to a consortium of Metropolitan, District, LBSCR, LCDR, and SER | |
| New Cross (1) to Surrey Quays started [Metropolitan] | ||
| 0 | New Cross (2) to Surrey Quays reopened [District] | |
| Surrey Quays to St. Mary's started [Metropolitan and District] | ||
| 1885- | GER joined the consortium leasing the ELR | |
| 1885-12-31 | Shoreditch to Liverpool Street withdrawn [LBSCR] | |
| 1886-01-01 | New Cross Gate to Liverpool Street started [GER] | |
| 1886-08-31 | New Cross (2) to Surrey Quays closed | |
| 1886-09-01 | New Cross Gate to Surrey Quays started [District] | |
| 1905-07-31 | New Cross Gate to St. Mary's withdrawn [District] | |
| 1905-08-01 | New Cross (1) to Whitechapel started [SE&CR] | |
| 1906-12-02 | New Cross (1) to Shadwell (1) withdrawn [Metropolitan] | |
| Shadwell (1) to St. Mary's closed | ||
| 1911-06-30 | Old Kent Road to Surrey Quays closed | |
| Services to south of New Cross (1) and New Cross Gate withdrawn | ||
| 1913-03-30 | All existing services withdrawn | |
| Shoreditch to Bishopsgate closed to passenger trains | ||
| 1913-03-31 | New Cross (1) to St. Mary's restored
![]() | |
New Cross Gate to Surrey Quays started
![]() | ||
Shadwell (1) to Shoreditch started
![]() | ||
| 1916-05-21 | ![]() |
Bishopsgate |
| 1916-12-31 | ![]() |
Old Kent Road |
| 1934-09-30 | ![]() |
Mildmay Park |
| 1938-04-30 | ![]() |
St. Mary's |
| 1940-05-05 | ![]() |
Haggerston |
| 1940-10-03 | ![]() |
Shoreditch NLR |
| 1941-10-05 | Shadwell (1) to St. Mary's closed | |
| 1948-01-01 | Transferred to LU ownership | |
| 1966-04-17 | Shoreditch to Liverpool Street closed to goods traffic | |
| 1986-06-27 | Broad Street to [Dalston West Junction] closed | |
| 1995-03-25 | New Cross (1) and New Cross Gate to Shoreditch closed | |
| 1998-03-25 | [4] | New Cross (1) and New Cross Gate to Whitechapel reopened |
![]() |
Canada Water | |
| 1998-09-27 | 0 | Whitechapel to Shoreditch reopened |
| 1999-08-19 | ![]() |
Canada Water |
| 2002-11-22 | ![]() |
Wapping (firefighters' strike) |
| 2002-11-30 | ![]() |
Wapping |
| 2006-06-09 | Whitechapel to Shoreditch closed | |
| 2007-12-22 | New Cross and New Cross Gate to Whitechapel closed | |
| 2010-07-01 | ? [9] | New Cross and New Cross Gate to Dalston Junction (re)opened |
![]() |
Shoreditch (NLR) | |
| ? | West Croydon and Crystal Palace to New Cross Gate started | |
| 2011-02- | ? | Dalston Junction to [Dalston West Junction] reopened |
| ? | [Dalston West Junction] to Highbury & Islington started | |
| 2012- | ? | Clapham Junction to Old Kent Road started |
| ? 1 | Old Kent Road to Surrey Quays reopened |
The original line was mostly double track, though Shoreditch station and the last section into each of New Cross (1) and New Cross Gate stations were single track. The extensions, including the route into New Cross Gate, will be double track on their own alignment, though the sections from Dalston Junction to Highbury & Islington and from New Cross Gate to West Croydon mostly use two of the tracks of a four-track line. The line is in tunnel from just north of Surrey Quays to Whitechapel, though some stations are in open cuttings. North of Whitechapel it rises on to viaduct for the section to Dalston Junction; the rest of the route is mostly at surface level. The Shoreditch branch was also in cutting and the National Rail lines into Liverpool Street still run past the end of Shoreditch station, though there has not been any connection since the late 1960s.
The line was initially electrified on the standard LU system, which it retained until closing in 2007, while the extended route (and the existing lines it connects to) is electrified throughout on the NR third-rail system. Some reports of the 1998 reopening state that the electrical systems can be operated in "third rail" or "fourth rail" mode but other sources disagree.
Although Shadwell (1) on this line and Shadwell (2) on the Docklands Light Railway are completely separate stations, interchange between the two on a single ticket is permitted.
Trains ran alternately to the two southern termini. Shoreditch was open in the peaks and on Sunday mornings, with all trains terminating alternately in the two platforms at Whitechapel at other times.
Minimum running time was 11 minutes to either southern terminus from Whitechapel.
Current plans are for a service of 4 trains per hour from Dalston Junction to each of New Cross, West Croydon, and Crystal Palace, and to Clapham Junction when that route opens (thus increasing the service from 12 to 16 trains per hour). Once the line is extended to Highbury & Islington, the New Cross and Crystal Palace services would continue to there.
<= North South =>
2 P /------N
/ \ /
2-H--D----------*-*-J-------Z--C /--L
V-S-/ / \ \ /
1 3-K \-*----G-----*-----R-3
\ / \
\ 3 X
\
M
C = Canal Junction
D = Dalston Junction
G = New Cross Gate
H = Highbury & Islington
J = Whitechapel Junction
K = Old Kent Road Junction
L = New Cross (2)
M = Clapham Junction
N = New Cross (1)
P = Spitalfields Goods Yard
R = West Croydon
S = Shoreditch
V = Liverpool Street
X = Crystal Palace
Z = Surrey Quays Junction
1 = link to St. Mary's Junction
2 = North London Line
3 = selected other NR lines (not all connections are shown)
Northbound is upwards on the page and southbound is downwards.
| 315847 | 41=54 | [=1NS2=7b] | ![]() |
{Highbury & Islington} | ||
| 319848 | 41=06 | [-] | [Canonbury West Junction] | |||
| 323850 | 40=62 | [=NS= b] | ![]() |
{Canonbury} | ||
| 328850 | 39=93 | [-] | (Mildmay Park) | |||
| 332850 | 39=65 | [-] | [Dalston West Junction] | |||
| 335847 | 39=21 | [=NS=we=] | ![]() |
{(Dalston Junction)} | ||
| 335838 | 38=34 | [ns =NS=] | ![]() |
{(Haggerston)} | ||
| 335830 | 37=5 | [ns =NS=] | ![]() |
{{Hoxton}} | ||
| 333826 | 37=08 | [ns =ns=] | (Shoreditch NLR) | |||
| 334823 | 36.71 | [-] | [end of NLR flyover from Broad Street, start of new flyover] | |||
| 335822 | 36.4 | [OP] | ![]() |
{{Shoreditch High Street}} | ||
| 345820 | 35.35 | [-] | [Spitalfields Junction] | |||
| 347818 | 35.23 | [OP4] | ![]() |
Whitechapel | ||
| 347816 | 34.99 | [-] | [Whitechapel Junction] | |||
| 349809 | 34.25 | [OP] | ![]() ![]() |
Shadwell (1) | ||
| 350801 | 33.47 | [OP] | ![]() ![]() |
Wapping | ||
| 352798 | 32.95 | [OP] | ![]() ![]() |
Rotherhithe | ||
| 354794 | 32.63 | [OPX2] | ![]() |
Canada Water | ||
| 355791 | 32.25 | [-] | [tunnel mouth] | |||
| 356789 | 32.08 | [OP] | ![]() |
Surrey Quays | ||
| 357785 | 31.63 | [-] | [Surrey Quays Junction] | |||
| 359779 | 30.98 | [-] | [Canal Junction] | |||
| 359779 | 30.98 | [-] | [depot entrance] | |||
| 360774 | 30.37 | [-] | [end of present single line] | |||
| 361773 | 30.36 | [-] | [depot exit] | |||
| 361770 | 29.90 | [=Nn=sS=S X] | ![]() |
New Cross Gate | ||
| 364757 | 28=57 | [=NnsS=] | ![]() |
{Brockley} | ||
| 358741 | 26=91 | [=NnsS=] | ![]() |
{Honor Oak Park} | ||
| 353729 | 25=48 | [=NnsS=] | ![]() |
{Forest Hill} | ||
| 353715 | 24=23 | [=NnsS=] | ![]() |
{Sydenham} | ||
| 24=05 | [-] | [Sydenham down Junction] | ||||
| 23=85 | [-] | [Sydenham up Junction] | ||||
| 349704 | 22=97 | [=NnsS=] | ![]() |
{Penge West} | ||
| 346699 | 22=32 | [=NnsS=] | ![]() |
{Anerley} | ||
| 340682 | 20=55 | [=N2=ns=SS=] | ![]() |
{Norwood Junction} | ||
| 335672 | 19=39 | [-] | [Norwood Fork Junction] | |||
| 331669 | 19=07 | [-] | [Gloucester Road Junction] | |||
| 321661 | 17=70 | [V= ^=ns=] | ![]() |
{West Croydon} | ||
| 332817 | 37=14 | [18 bays] | {Liverpool Street} | |||
| 335822 | 36=46 | [=NS= wewe] | (Bishopsgate) | |||
| 338822 | 36=16 | [-] | [East London Junction] | |||
| 339821 | 36.03 | [=1V =] | ![]() |
Shoreditch | ||
| 343821 | 35.6 | [-] | [convergence with current route] | |||
| 342816 | 35.49 | [OP] | (St. Mary's) | |||
| 343817 | 35!45 | [-] | [St. Mary's Junction] | |||
| 347816 | 34.99 | [-] | [Whitechapel Junction] | |||
| 359779 | 30.98 | [-] | [Canal Junction] | |||
| 363777 | 30.51 | [-] | [end of single line] | |||
| 364777 | 30.40 | [-] | [Depot entrance] | |||
| 366771 | 29.78 | [wew'A'='B'be'C'='D'V] | ![]() |
New Cross (1) | ||
| 360774 | 30.37 | [-] | [approximate point of divergence from current route] | |||
| 362771 | 30.1 | [VV] | (New Cross (2)) | |||
| 24=05 | [-] | [Sydenham down Junction] | ||||
| 23=85 | [-] | [Sydenham up Junction] | ||||
| 341705 | 22=22 | [=NS=du= X] | ![]() |
{Crystal Palace} | ||
| 356789 | 32.08 | [OP] | ![]() |
Surrey Quays | ||
| 357785 | 31.63 | [-] | [Surrey Quays Junction] | |||
| 356782 | 31.07 | [-] | [northbound and southbound converge] | |||
| 355779 | 30.90 | [-] | ![]() |
{{Surrey Canal Road}} | ||
| 352774 | 30.14 | [-] | [Old Kent Road Junction] | |||
| 352773 | 30=0 | [-] | (Old Kent Road) | |||
| 350768 | 29=51 | [IP] | ![]() |
{Queens Road Peckham} | ||
| 341762 | 28=34 | [=ew= N=S X] | ![]() |
{Peckham Rye} | ||
| 339762 | 28=12 | [-] | [Peckham Rye Junction] | |||
| 331762 | 27=28 | [-] | [Grove Tunnel east portal] | |||
| 329761 | 27=17 | [-] | [Grove Tunnel west portal] | |||
| 328761 | 26=99 | [=ew=NS= X] | ![]() |
{Denmark Hill} | ||
| 327760 | 26=87 | [-] | [Denmark Hill Tunnel east portal] | |||
| 326760 | 26=81 | [-] | [Denmark Hill Tunnel west portal] | |||
| 305755 | 24=48 | [-] | [Shepherds Lane Junction] | |||
| 298757 | 23=82 | [ew =NS= X] | ![]() |
{Clapham High Street} | ||
| 294762 | 23=19 | [ew =NS= X] | ![]() |
{Wandsworth Road} | ||
| 293763 | 23=07 | [-] | [Factory Junction east] | |||
| 292764 | 22=89 | [-] | [Factory Junction west] | |||
| 287766 | 22=25 | [-] | [Longhedge Junction A] | |||
| 286765 | 22=15 | [-] | [Longhedge Junction B] | |||
| 285764 | 22=07 | [-] | [Longhedge Junction C] | |||
| 273757 | 20=64 | [-] | [Ludgate GW Junction] | |||
| 271756 | 20=29 | [b=Bbw=ew=ew] | ![]() |
{Clapham Junction} | ||
| 268754 | 19=93 | [-] | [end of sidings] | |||
The line was served by New Cross Depot, a small depot on the west side of the New Cross branch, with major work done by running trains to Neasden Depot on the Metropolitan Line. A new train servicing facility is being built just north of New Cross Gate and heavier work will be done at the existing depot at Selhurst.
Until early 2008 a double track link connected the line to the District Line just east of St. Mary's station (now closed). Eastbound District trains could run over the link to become southbound East London Line trains south of Whitechapel; similarly northbound ELL trains can become westbound District trains. Links to the main lines at Shoreditch, New Cross, and New Cross Gate were removed around 1970.
The conversion to a LO line will create new links at Dalston and Old Kent Road and restore the link at New Cross Gate.
For the last years of its life under LU the line was operated by 4-car A stock trains (using units with both cabs equipped); these were part of the Metropolitan Line fleet and exchanged with that line on a regular basis.
The only trains that were permitted to carry passengers were 4-car A stock (where both cabs are equipped), 4-car C stock, and 3 car double-ended units of 1973 Tube Stock (passengers were not allowed to board or alight from 1973 Tube Stock at Canada Water due to the higher platforms). Longer trains, including 1959, 1967, and 1972 Tube Stock could carry passengers non-stop from Aldgate East or Whitechapel to New Cross Gate, or could run directly into New Cross Depot (though limited to certain sidings there). 4-car trains of those stocks could operate empty anywhere on the line. The erstwhile link to the District Line, though double track, coluld not be used in both directions simultaneously due to insufficient clearance. Following the reconstruction of 1995-8, the line was cleared for main line "Networker" trains.
When the line re-opens, it is currently expected that it will be operated by class 378 Electrostar EMUs.
Back to the CULG index.
Back to the Rail
index.
Back to
Clive's home page.